Owner: Texas Department of Transportation
Start Date:
December 2022

Description: North Star Trenchless, LLC has partnered with Jordan Foster and others on a TxDOT project that involves relocation of existing El Paso Water (EPW) 48-inch water line in order to widen State Loop 375 (SL375).  NST scope of work includes pit excavation and installation of 2,836 linear feet of 66-inch and 485 liner feet of 54-inch Hobas direct jack pipe to be utilized as casing pipe.  There is a total of 9 tunnels on this project and lengths range from 43 to 700 linear feet.  Soil conditions are caliche and sand.  Pipe jacking/tunneling methods with TBM are being utilized to install.